L
Luca
Hi There,
A client has asked if an anticipated finish var. column could be added to
show how late (or early) a task is anticipated to finish, i.e 10days, -2days
etc.
He has said that the anticipated date is to be calculated using the overall
duration of the task, multiplied by by the %complete plus the current delay,
i.e task goes for 29 days and 90% complete, therefore = 3 days left to
complete plus current delay which is current date (say 06/02/09) less
programme finish date (say 05/12/08) = 64 days behind schedule (3 + 61). So
in the anticipated column you would have in there -64 days.
I have a Finish Var column but obviously that shows '0' until I insert an
actual finish date so then the programme can compare the planned finish date
to the actual finish date and establish the difference.
Can someone please explain if you can have an anticipated finish var. column
and how I can set up the formula so it reflects what I have explained above.
Many Thanks - Luca
A client has asked if an anticipated finish var. column could be added to
show how late (or early) a task is anticipated to finish, i.e 10days, -2days
etc.
He has said that the anticipated date is to be calculated using the overall
duration of the task, multiplied by by the %complete plus the current delay,
i.e task goes for 29 days and 90% complete, therefore = 3 days left to
complete plus current delay which is current date (say 06/02/09) less
programme finish date (say 05/12/08) = 64 days behind schedule (3 + 61). So
in the anticipated column you would have in there -64 days.
I have a Finish Var column but obviously that shows '0' until I insert an
actual finish date so then the programme can compare the planned finish date
to the actual finish date and establish the difference.
Can someone please explain if you can have an anticipated finish var. column
and how I can set up the formula so it reflects what I have explained above.
Many Thanks - Luca