M
Michelle
I have used the task splitting functionality in Project
before but I'm now preparing to use it on a project plan
that is larger than what I've previously managed. One
thing that has bothered me in the past is that if you
split a task to eliminate a resource overallocation and
then your schedule changes, you have to go back and remove
the split and recreate it at a new point in the schedule
because it is not tied to the other task that you split it
to accomodate and therefore does not automatically
adjust. I am not thrilled with the prospect of having to
do this over and over again each time there is a change to
the project plan. This project has a lot of longer
duration tasks that need to be interrupted temporarily to
allow the resources to complete smaller tasks. Any
suggestions on how to make this less painful?
Maybe someone can suggest a better way to manually
resource level (the automatic levelling funciton in
project does not produce a schedule I can live with).
before but I'm now preparing to use it on a project plan
that is larger than what I've previously managed. One
thing that has bothered me in the past is that if you
split a task to eliminate a resource overallocation and
then your schedule changes, you have to go back and remove
the split and recreate it at a new point in the schedule
because it is not tied to the other task that you split it
to accomodate and therefore does not automatically
adjust. I am not thrilled with the prospect of having to
do this over and over again each time there is a change to
the project plan. This project has a lot of longer
duration tasks that need to be interrupted temporarily to
allow the resources to complete smaller tasks. Any
suggestions on how to make this less painful?
Maybe someone can suggest a better way to manually
resource level (the automatic levelling funciton in
project does not produce a schedule I can live with).