A
anovak
Does it matter if they write over the Remaining Work value before they
run out of hours? If I've added Forecast Finish date to the grid,
should they update the Finish date and let My Task recalc the
Remaining Hours, or enter Remaining Hours and let My Tasks recalc the
current Finish Date?
Should they enter their daily hours, select recalc, THEN observe
Remaining Hours and overlay if needed?
Any and all info concerning this would be appreciated.
Thanks,
Andy Novak
UNT
run out of hours? If I've added Forecast Finish date to the grid,
should they update the Finish date and let My Task recalc the
Remaining Hours, or enter Remaining Hours and let My Tasks recalc the
current Finish Date?
Should they enter their daily hours, select recalc, THEN observe
Remaining Hours and overlay if needed?
Any and all info concerning this would be appreciated.
Thanks,
Andy Novak
UNT