Dear All,

My Manager need to genereate report from administrive time.
Does anyone know how to create a report that contains how many days
in a month or week that a resource take personal leave or administrative item?
other ?
Could i use ms Project VBA? or i should use SDK?
thanks

Rully
 
D

Dale Howard [MVP]

Rully --

If you are using Project Server 2007, you can use the three
Timesheet-related OLAP cubes that contain this type of information. Hope
this helps.




"Project Getting Queued problem"
 
J

Jonathan Sofer

If those cubes doen't give you enough information, you can always install
SQL Reporting Services 2005 and create your own reports based off the
Published and Reporting databases.

Jonathan
 