Using MS Project Server 2007 and Timesheets.

I have several task updates that were cancelled in the Queue. They now
display in PWA Task Updates page in the Applied Requests and Errors view as
"X" errors. each task is labeled as accepted by the PM.

How do I get these to push into the project plan or back to the task updates
page to re-approve? I tried using the Sync Protected Actuals feature in the
plan, but nothing happen.
 
D

Dale Howard [MVP]

Mike --

I think you need to ask the team members to resubmit their updates so that
the PMs can reapprove them. Hope this helps.
 
M

Mike Fisher

That is unfortunate. I will try this and see if the updates are resent.

Thank you Dale.
 
D

Dale Howard [MVP]

Mike --

You are more than welcome for the help, my friend. :)




Mike Fisher said:
That is unfortunate. I will try this and see if the updates are resent.

Thank you Dale.
 