H
Huckey
Hi all,
StatusApprovalsHistory.aspx in PWA shows all task update requests
and errors applied to project assignments. For some reason though it
is not possible to export the data displayed there to Excel which I am
interested in.
How can I export the data about task updates to Excel? If I can not
do it form PWA, how can I get the equivalent dataset from MS SQL
Server? I have found table MSP.ASSIGNMENTS_TRANSACTIONS but there the
data about dates and % complete is stored as binary data so I could
not see the details.
I am using MS Project Server 2007 on MS SQL Server 2005.
Thanks!
Best regards
Huckey
StatusApprovalsHistory.aspx in PWA shows all task update requests
and errors applied to project assignments. For some reason though it
is not possible to export the data displayed there to Excel which I am
interested in.
How can I export the data about task updates to Excel? If I can not
do it form PWA, how can I get the equivalent dataset from MS SQL
Server? I have found table MSP.ASSIGNMENTS_TRANSACTIONS but there the
data about dates and % complete is stored as binary data so I could
not see the details.
I am using MS Project Server 2007 on MS SQL Server 2005.
Thanks!
Best regards
Huckey