M
Mila
I have a large resource group - 27 people (shown as 2700%)
I need them to each not be working at 100% of the 8 hour day they are
attached to in a calendar.
I would like to reduce the day in the calendar the resources are using to 7
hours without changing the duration of the project - just using more
resources. Suggestions?
I'm limited to the 2003 version.
I need them to each not be working at 100% of the 8 hour day they are
attached to in a calendar.
I would like to reduce the day in the calendar the resources are using to 7
hours without changing the duration of the project - just using more
resources. Suggestions?
I'm limited to the 2003 version.