I am in an Project Server environment (2003), with multiple resources
available to me that also work on other projects. I have read that in this
scenario, it is best to set Max Units to the percent ea. is available to work
on my project. However, this option is grayed out.
This being said, how can I allow for persons working on multiple projects?
Should I just set ea. person's assignment-related Units to less than 100%?
Also, if applying multiple resources to a task, as I must do to allow ea. to
put time against the tasks/s, in PWA, how can I know who will do what
percentage of the work? I can set the work evenly accross them, but after
updates in PWA, they will change.
available to me that also work on other projects. I have read that in this
scenario, it is best to set Max Units to the percent ea. is available to work
on my project. However, this option is grayed out.
This being said, how can I allow for persons working on multiple projects?
Should I just set ea. person's assignment-related Units to less than 100%?
Also, if applying multiple resources to a task, as I must do to allow ea. to
put time against the tasks/s, in PWA, how can I know who will do what
percentage of the work? I can set the work evenly accross them, but after
updates in PWA, they will change.