Approval after Lockdown...

M

MD

OK is it normal that after a managed time frame is locked, that the project
manager can still approved time that was within that timeframe?

i.e. 12/01/05 - 12/31/05 is locked but time still remains to be approved...
Project Manager approves time that was submitted prior to the lockdown and it
allows them to. Please explain if possible.
 
D

Dale Howard [MVP]

MD --

The "locked down" aspect of a time period is used to prevent a team member
from entering actuals in that time period. Hope this helps.
 