A
Andrew Stokes
Hi
When approving planned administrative (Vacation etc.) there seems to be
little detail available for the the approver to make a valid judgement on
approval.
Say for instance I submit planned administrative time for a vacation which
requires approval. The approver only sees the start and end dates, category
description and resource name. This seems to give little insight into what
needs approving.
Is there any way to give some more detail to the approver e.g. hours
requested for each day. If a resource requests 1 day of vacation in a week
the approver won't know on which day the vacation is planned.
Regards
Andy
When approving planned administrative (Vacation etc.) there seems to be
little detail available for the the approver to make a valid judgement on
approval.
Say for instance I submit planned administrative time for a vacation which
requires approval. The approver only sees the start and end dates, category
description and resource name. This seems to give little insight into what
needs approving.
Is there any way to give some more detail to the approver e.g. hours
requested for each day. If a resource requests 1 day of vacation in a week
the approver won't know on which day the vacation is planned.
Regards
Andy