Laurent Bacha
Hello.
The approval of the modifications of the tasks is a good thing(matter) if it
is not too invasive: the fact that a resource changes the % of work realized
on an intermediate task is not very useful.
Where can we parametrize the approval as follows (for example):
Necessary Approval for:
- change of dates (before or after).
- change of the workload.
- realization of a ranging-pole task (100 % of realized work).
Not approval for:
- progress of a non-ranging-pole task (change % realized work).
Is it possible to have a so fine detail globally for a whole population of
users and projects ?
Sincerly,
Laurent.
The approval of the modifications of the tasks is a good thing(matter) if it
is not too invasive: the fact that a resource changes the % of work realized
on an intermediate task is not very useful.
Where can we parametrize the approval as follows (for example):
Necessary Approval for:
- change of dates (before or after).
- change of the workload.
- realization of a ranging-pole task (100 % of realized work).
Not approval for:
- progress of a non-ranging-pole task (change % realized work).
Is it possible to have a so fine detail globally for a whole population of
users and projects ?
Sincerly,
Laurent.