Approved abd unapproved time

A

Atease

Hi ,

is there a way to see time which has been approved by the project
manager and time which was actually logged by a resource. I created a
pivot table with Actual Work (hourses closked by resource) and
Actual Work protected (approved hours), but it gives the same figure
and I can se ethat there is still time which is unapproved.

Is these any other field or way I can find this out.

Thanks
 
J

JulieS

Hi Atease,

I assume you are working with Project Server as you are referring to
project manager's approval for actual time. I suggest re-posting your
question to the Project Server newsgroup. The majority of the server
gurus spend more time in the server newsgroup than here so you may get a
more rapid response there.

I hope this helps.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 