Approved task update through PWA, does not update task in Project

C

Chris

My resource has submitted task progress updates through PWA. I review the %
update and approve it. The overall task status in the Project Center does
not change. That specific task which is now say 80% complete remains 0. If
the recourse looks at their "My Task" view, the task sits at 80%.

If I open MS Project (client) and look at the same task, the task has the
newly changed progress to 80%. Any ideas?
 
D

Dale Howard [MVP]

Chris --

You have to publish your project before the changes show up in the Project
Center. This means that at the end of every round of accepting task
updates, your PMs need to publish the latest changes to their projects.
Hope this helps.
 