A
Andrzej Jaworek
I'm using Project Web Access 2007 + Project 2007.
I'm an PWA administrator.
I have a project named Test that has a owner named Chris.
I can open this project and add tasks to it (because I'm administrator).
After adding tasks (with work resource assignment) to the project Test
and publishing it, tasks are sended to the users that are assigned to.
They can report status of their tasks using Task Center. After doing
that approving tasks updates are sended to ME NOT to CHRIS ? Why? Chris
is the owner of this project so he should manage approving task for his
project. If Chris open the project in Project 2007 and add task to it
and publish it everything works correctly. He receive this task updates
for approve.
What should I do to allow Chris receiving ALL task updates from his
project regardless of who is adding the tasks (he or me).
Please help.
Thank You in advance.
Andy
I'm an PWA administrator.
I have a project named Test that has a owner named Chris.
I can open this project and add tasks to it (because I'm administrator).
After adding tasks (with work resource assignment) to the project Test
and publishing it, tasks are sended to the users that are assigned to.
They can report status of their tasks using Task Center. After doing
that approving tasks updates are sended to ME NOT to CHRIS ? Why? Chris
is the owner of this project so he should manage approving task for his
project. If Chris open the project in Project 2007 and add task to it
and publish it everything works correctly. He receive this task updates
for approve.
What should I do to allow Chris receiving ALL task updates from his
project regardless of who is adding the tasks (he or me).
Please help.
Thank You in advance.
Andy