J
JodyJ
In reading an excerpt from
http://www.projectserverexperts.com/Shared Documents/ArchiveCompletedProjects.htm,
there is a step re: removing tasks from resources timesheets. See below:
When a project team completes a project, the project manager should
immediately do the following:
1. Open the completed project in Microsoft Project Professional
2. Click Project - Project Information, set the Production Status field
value to Completed, and then click OK
3. Click Tools - Build Team from Enterprise
4. Set the Booking value for each project team member to Proposed and
then click OK
5. Click Collaborate - Publish - All Information
6. Save and close the completed project
My question is this: What effect does this have on reporting of "actual
work" for that project? We still want to report on these projects.
http://www.projectserverexperts.com/Shared Documents/ArchiveCompletedProjects.htm,
there is a step re: removing tasks from resources timesheets. See below:
When a project team completes a project, the project manager should
immediately do the following:
1. Open the completed project in Microsoft Project Professional
2. Click Project - Project Information, set the Production Status field
value to Completed, and then click OK
3. Click Tools - Build Team from Enterprise
4. Set the Booking value for each project team member to Proposed and
then click OK
5. Click Collaborate - Publish - All Information
6. Save and close the completed project
My question is this: What effect does this have on reporting of "actual
work" for that project? We still want to report on these projects.