Are Enterprise Custom fields at the Project Level at Task Level?

A

Al Himler

We've set up a Project level Enterprise Custom Field. It is a simple color
code (Red, Yellow, Green). We have a program that uses the PDA interface to
retrieve data from projects, but we don't understand the results that are
coming back - it looks like that for a given project we get a record back for
each Task when we are querying for the value in the Project Enterprise Custom
Field.

Example: Project level Enterprise Custom Field is "Client Satisfaction"
with possible values of Red, Yellow, Green. Using MS Project on a specific
project, we set the value to "Red" on the Project Information dialog and
publish the project on Project Server. The project has 10 tasks in it. Our
application that queries through PDA to get the value of the field, doesn't
get the value "Red" back, it gets the value "Red" back 10 times.

Any ideas on what that might be?

Thanks,

Al
 