D
Dan Haydon
Hi all,
Our shop uses MSPS which is integrated with MOSS. If I set a task to Fixed
Units (a % of total resource utilization across all PM's), then the resource
updates their time in MOSS and then I accept the time against the schedule,
the resources utilization on the task moves from the original % designation.
Shouldn't the other variables change and leave the Units fixed, as designated?
Also, using server is there a way to set the resource allocation at the
project level instead of the task level? When I go to enter at the project
level I get a message saying something to the effect that it will be
overridden by the global %'s.
Thanks!
Dan
Our shop uses MSPS which is integrated with MOSS. If I set a task to Fixed
Units (a % of total resource utilization across all PM's), then the resource
updates their time in MOSS and then I accept the time against the schedule,
the resources utilization on the task moves from the original % designation.
Shouldn't the other variables change and leave the Units fixed, as designated?
Also, using server is there a way to set the resource allocation at the
project level instead of the task level? When I go to enter at the project
level I get a message saying something to the effect that it will be
overridden by the global %'s.
Thanks!
Dan