For Project Client 2007
939595 PRJ2007 After checking resource information a project crash is
soon
to happen
939595 PSVR2007 - Renaming projects breaks cross project links.
939595 PRJ2007 - Leveling does not correctly updated Finish date of
tasks
939163 PRJ2007 - Adding values to outline codes shows linear
performance
degradation, is significantly slower than P11
939162 PRJ2007 - Object Model does not allow the use of assignment
enterprise text fields.
938889 PRJ2007 - Migrated custom fields do not show changes when
modified
938889 PRJ2007 - Cut and paste to indented task does not indent
pasted task
938889 PRJ2007 - Project Professional sending parent-less assignments
to
the system
938886 PRJ2007 - Incorrect code mask allows additional items to be
entered.
938889 PRJ2007 : Outline codes are not indented in Grouping views
938189 PRJ2007 - Enterprise Custom Fields are not sorted in
alphabetical
order
937907 PRJ2007 - Enterprise Outline Codes changes not saved when
changed in
Project Information
937907 PRJ2007 - Projects remain in a "Checkin Pending" state
937907 PRJ2007 - Status manager field should not be saved with a
template.
936517 PRJ2007: You cannot use the Fill Down feature for the Status
Manager
field in templates.
935557 PRJ2007 Importing plans the import wizard doesn't
automatically map
to the Enterprise Account
For Project Server 2007
939594 PSVR2007 : OLAP cube dimensions do not work (dpk already
created)
939161 PSVR2007 - Reporting database does not contain the capacity
value
for Generic Resources
938891 PSVR2007 - Assignments with Proposed Resources are published
to PWA
and visible in My Tasks
937908 PSVR2007 - Use of local calendar results in variance between
PWA and
Pro views
937908 PSVR2007 - Task Updates need improved visibility
PendingPSVR2007 homepage performance degrades with lots of risks or
issues
(sometimes the page will timeout)
937908 PSVR2007 - DCR - My Tasks Page - Need Collapse Functionality
937908 PSVR2007 - Deny the 'Create new Activity or Proposal' global
permission causes an error in Build Team from Enterprise.
937908 PSVR2007: Users get 'An unexpected error has occurred' when
accessing the PWA homepage
937908 PSVR2007 -DCR- Task IDs are unavailable for My Work views.
937908 PSVR2007 -DCR- Task IDs are unavailable when creating new task
in PWA.
937908 PSVR2007 -DCR- Unable to enter work estimate when creating new
task
in PWA.
937908 PSVR2007 Can't change the owner of a project plan in PWA
937908 PRJSVR2007 Unable to link an issue to a task when the task
number is
greater than 100
PendingPSVR2007 Syncing to WSS Root site can take up to what appears
to be
48 hours
937908 PSVR2007 Drilling into Project from the Project Center can be
slow
937908 PSVR2007 Cleanup of FAC feature from code base presence limits
scalability
937476 PSVR2007 CDCR: My Tasks page doesn't show a total before
submitting
to the PM for approval
936876 PSVR2007 Using Export to Excel doesn't bring over all
pertinent
information
936134 PSVR2007 : Timesheet totals don't display if you turn off the
"The
timesheet will use standard Overtime and Non-Billable time tracking."
options
936134 PSVR2007 Extreme waiting for common PSI calls when transferred
data
is certain size
(see below)? If so, please let me know which KBs are newly available.
Thanks,
Andy Novak
UNT
For Project Client 2007
939595 PRJ2007 After checking resource information a project crash is
soon
to happen
939595 PSVR2007 - Renaming projects breaks cross project links.
939595 PRJ2007 - Leveling does not correctly updated Finish date of
tasks
939163 PRJ2007 - Adding values to outline codes shows linear
performance
degradation, is significantly slower than P11
939162 PRJ2007 - Object Model does not allow the use of assignment
enterprise text fields.
938889 PRJ2007 - Migrated custom fields do not show changes when
modified
938889 PRJ2007 - Cut and paste to indented task does not indent
pasted task
938889 PRJ2007 - Project Professional sending parent-less assignments
to
the system
938886 PRJ2007 - Incorrect code mask allows additional items to be
entered.
938889 PRJ2007 : Outline codes are not indented in Grouping views
938189 PRJ2007 - Enterprise Custom Fields are not sorted in
alphabetical
order
937907 PRJ2007 - Enterprise Outline Codes changes not saved when
changed in
Project Information
937907 PRJ2007 - Projects remain in a "Checkin Pending" state
937907 PRJ2007 - Status manager field should not be saved with a
template.
936517 PRJ2007: You cannot use the Fill Down feature for the Status
Manager
field in templates.
935557 PRJ2007 Importing plans the import wizard doesn't
automatically map
to the Enterprise Account
For Project Server 2007
939594 PSVR2007 : OLAP cube dimensions do not work (dpk already
created)
939161 PSVR2007 - Reporting database does not contain the capacity
value
for Generic Resources
938891 PSVR2007 - Assignments with Proposed Resources are published
to PWA
and visible in My Tasks
937908 PSVR2007 - Use of local calendar results in variance between
PWA and
Pro views
937908 PSVR2007 - Task Updates need improved visibility
PendingPSVR2007 homepage performance degrades with lots of risks or
issues
(sometimes the page will timeout)
937908 PSVR2007 - DCR - My Tasks Page - Need Collapse Functionality
937908 PSVR2007 - Deny the 'Create new Activity or Proposal' global
permission causes an error in Build Team from Enterprise.
937908 PSVR2007: Users get 'An unexpected error has occurred' when
accessing the PWA homepage
937908 PSVR2007 -DCR- Task IDs are unavailable for My Work views.
937908 PSVR2007 -DCR- Task IDs are unavailable when creating new task
in PWA.
937908 PSVR2007 -DCR- Unable to enter work estimate when creating new
task
in PWA.
937908 PSVR2007 Can't change the owner of a project plan in PWA
937908 PRJSVR2007 Unable to link an issue to a task when the task
number is
greater than 100
PendingPSVR2007 Syncing to WSS Root site can take up to what appears
to be
48 hours
937908 PSVR2007 Drilling into Project from the Project Center can be
slow
937908 PSVR2007 Cleanup of FAC feature from code base presence limits
scalability
937476 PSVR2007 CDCR: My Tasks page doesn't show a total before
submitting
to the PM for approval
936876 PSVR2007 Using Export to Excel doesn't bring over all
pertinent
information
936134 PSVR2007 : Timesheet totals don't display if you turn off the
"The
timesheet will use standard Overtime and Non-Billable time tracking."
options
936134 PSVR2007 Extreme waiting for common PSI calls when transferred
data