R
Rick Williams
There are a number of highly-paid consultants in the project management field
who make their living by convincing management that they can give them
valuable assistance in managing their project by performing a so-called
"top-level" schedule risk analysis. I have been doing schedule risk analysis
for over 20 years, and I believe in doing them "the hard way" - I use the
most detailed schedules I can get, and have the people who are doing the work
estimate optimistic and pessimistic durations, then use a Monte Carlo
simulation tool to find all the possible critical paths, and provide
management with detailed information on what areas of the project should
receive the most management attention and resources in order to increase the
probability of success. And I am good at it.
But still, management often falls for the claims of these outside
consultants. They come in and interview a handful of people and try to find
out what people think are the high-risk areas in the project. Then they build
a small schedule network and use some Monte Carlo tool on it, then they write
their report. In every case I have seen, this report simply regurgitates the
information from the interviews - garbage in, garbage out. They could just as
well have skipped the Monte Carlo analysis part - they are using it to make
it look like their answer is "scientifically" derived.
So, how does one argue against this and keep management from wasting money?
who make their living by convincing management that they can give them
valuable assistance in managing their project by performing a so-called
"top-level" schedule risk analysis. I have been doing schedule risk analysis
for over 20 years, and I believe in doing them "the hard way" - I use the
most detailed schedules I can get, and have the people who are doing the work
estimate optimistic and pessimistic durations, then use a Monte Carlo
simulation tool to find all the possible critical paths, and provide
management with detailed information on what areas of the project should
receive the most management attention and resources in order to increase the
probability of success. And I am good at it.
But still, management often falls for the claims of these outside
consultants. They come in and interview a handful of people and try to find
out what people think are the high-risk areas in the project. Then they build
a small schedule network and use some Monte Carlo tool on it, then they write
their report. In every case I have seen, this report simply regurgitates the
information from the interviews - garbage in, garbage out. They could just as
well have skipped the Monte Carlo analysis part - they are using it to make
it look like their answer is "scientifically" derived.
So, how does one argue against this and keep management from wasting money?