As late as possible and as soon as possible on same task?

U

Udderjuice

Hi everyone. I am wondering if it is possible to set the "as soon as
possible" and the "as late as possible" restraint on the same task. I have
single-day, monument events that control the start and finish of my other
tasks and I don't want to have to adjust the duration for the dependant tasks
when I move the monuments around. Any suggestions? Thanks.
 
M

Mike Glen

Hi Udderjuice ,

Welcome to this Microsoft Project newsgroup :)

No. However, you shouldn't need to adjust the Durations of subsequent tasks
unless you've entered dates in the Start or Finish fields, as these will
thus have constraints. Without constraints, the successor tasks will
automatically adjust.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 