Hi,
when scheduling part of a project (several dependant F-S tasks) ALAP, i'm
receiving negative total slack only at the last task of the path. all other
tasks apears as TS=0.
when scheduling same path ASAP - negative slack appears to the whole path.
why? any ideas?
thanks in advance,
Ido.