Thats my question:
How can i easily asign many tasks to the same resource? not doing one by
one, obviously....
Thank you!!!

Te Pregunto
 
D

Dale Howard [MVP]

TP --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is dedicated to
the Microsoft Project desktop application only. To answer your question,
click the Assign Resources button on the Standard toolbar. This opens the
Assign Resources dialog. In the Task Sheet on the left side of your Gantt
Chart, select the tasks to which you wish to assign the resource. In the
Assign Resources dialog, select a resource, specify the Units for the
resource (to indicate full-time or part-time work) and then click the Assign
button. NOTE: If you want to assign multiple resources to a task, use the
Control key to select the resources as a batch, but you CANNOT set a
different Units value for each resource. Instead, select the batch of
resources and then click the Assign button. Hope this helps.
 