D
DGD
I am laying out a project plan and am trying to determine a few
things. First, I would like to get a roll up of the labour costs
associated with a project. I have added an additional column and
assigned the "Cost" field to it. This is the only way to list the
costs of the project that I can find. The problem that I have is that
the "cost" field appears to be pre-programmed to to calculate total
costs, meaning the sum of resources and fixed costs allocated to a
task. I want to be able to assign resource costs to a user
configurable field, like "cost1, cost2, etc" but the resource costs
never appear when I try this. They seem to only be programmed to
appear in the "cost" field, and given that it is pre-programmed to add
both resource and fixed costs, trying to separate the two costs is
really problematic.
When I use the fixed cost column, I can never get the fixed costs to
roll up to get a summary, regardless of level. They are there in the
task row, but just won't roll up to higher level tasks or the top
summary line. Don't understand what going on here.
The third problem I am having is trying to allocate daily expenses.
For instance, on a trip there are $200/day per diem I want to assign
for the duration of the trip. If the trip was 6 days long, I would
allocate 600% of the per diem rate to generate a cost of $1,200
dollars. The resource called "per diem" has a $200/use identified in
the resource sheet. It totals up the numbers nicely, but for some
reason, it also allocates 6 days of work in the "work" column, skewing
my level of effort numbers. I can treat them as fixed costs, but it
is a pain to go in and get to the tables to enter fixed costs. If I
change the length of the trip, I have to go to 2 different places to
update the project plan - the resource allocation and the fixed cost
tables. Are there any easier ways of doing this?
Any help greatly appreciated.
Doug
things. First, I would like to get a roll up of the labour costs
associated with a project. I have added an additional column and
assigned the "Cost" field to it. This is the only way to list the
costs of the project that I can find. The problem that I have is that
the "cost" field appears to be pre-programmed to to calculate total
costs, meaning the sum of resources and fixed costs allocated to a
task. I want to be able to assign resource costs to a user
configurable field, like "cost1, cost2, etc" but the resource costs
never appear when I try this. They seem to only be programmed to
appear in the "cost" field, and given that it is pre-programmed to add
both resource and fixed costs, trying to separate the two costs is
really problematic.
When I use the fixed cost column, I can never get the fixed costs to
roll up to get a summary, regardless of level. They are there in the
task row, but just won't roll up to higher level tasks or the top
summary line. Don't understand what going on here.
The third problem I am having is trying to allocate daily expenses.
For instance, on a trip there are $200/day per diem I want to assign
for the duration of the trip. If the trip was 6 days long, I would
allocate 600% of the per diem rate to generate a cost of $1,200
dollars. The resource called "per diem" has a $200/use identified in
the resource sheet. It totals up the numbers nicely, but for some
reason, it also allocates 6 days of work in the "work" column, skewing
my level of effort numbers. I can treat them as fixed costs, but it
is a pain to go in and get to the tables to enter fixed costs. If I
change the length of the trip, I have to go to 2 different places to
update the project plan - the resource allocation and the fixed cost
tables. Are there any easier ways of doing this?
Any help greatly appreciated.
Doug