E
Erdem Seherler
My full time resource turned to part-time in one of my projects. She will
only work at thursdays and fridays I have created an enterprise calendar by
copying from my standart calendar. I have made only thursday and fridays as
work day.
I have opened my project, changed into resource usage view. Clicked the
resource information. Clicked change working time button at general view.
But I cannot change the base calendar. It is disabled. I hope to change the
base calendar to new calendar I have created for only this project, and for
this resource.
Note 1: I don't want to change the base calendar for the resource at pwa,
edit resource page.
Note 2: I have some actual works at past weeks for my resource as full time
worked. Don't want them to change.
How can I find a way for my resources remaining works to get planned for
thursday and fridays,
any help is appriciated,
best regards
only work at thursdays and fridays I have created an enterprise calendar by
copying from my standart calendar. I have made only thursday and fridays as
work day.
I have opened my project, changed into resource usage view. Clicked the
resource information. Clicked change working time button at general view.
But I cannot change the base calendar. It is disabled. I hope to change the
base calendar to new calendar I have created for only this project, and for
this resource.
Note 1: I don't want to change the base calendar for the resource at pwa,
edit resource page.
Note 2: I have some actual works at past weeks for my resource as full time
worked. Don't want them to change.
How can I find a way for my resources remaining works to get planned for
thursday and fridays,
any help is appriciated,
best regards