assign different calendar to resource

E

Erdem Seherler

My full time resource turned to part-time in one of my projects. She will
only work at thursdays and fridays I have created an enterprise calendar by
copying from my standart calendar. I have made only thursday and fridays as
work day.

I have opened my project, changed into resource usage view. Clicked the
resource information. Clicked change working time button at general view.
But I cannot change the base calendar. It is disabled. I hope to change the
base calendar to new calendar I have created for only this project, and for
this resource.

Note 1: I don't want to change the base calendar for the resource at pwa,
edit resource page.
Note 2: I have some actual works at past weeks for my resource as full time
worked. Don't want them to change.

How can I find a way for my resources remaining works to get planned for
thursday and fridays,

any help is appriciated,
best regards
 
B

Ben Howard

Hi Erdem,
You need to change it at the resource level, so open the resource from the
enterprise resource pool and change the calendar there. The, open the
project, and re-calc the project. The assignments for that resource should
now change. Existing work should not be effected.
 