J
JmpJack
Maybe I don't understand Project Server well enough, but here is my question:
We have encountered an interesting quirk within MSPS that we have a question
on. Here's the scenario:
1) create a new task in a project professional 2003 (Task type is set
to fixed work)
2) assign resource(s) to the task
3) save and publish the project
4) additional resource uses web access to assign the same task to
him/herself
5) project manager accepts the task in project
6) MSPS assigns the additional resource to the task, then splits the
time AND reduces the amount of work for the task. (the fixed work)
Our issue is with the reduction of the amount of work for a 'Fixed Work'
task. Why is the amount of work reduced? Any explanation of what is
happening?
Thanks
jmp
We have encountered an interesting quirk within MSPS that we have a question
on. Here's the scenario:
1) create a new task in a project professional 2003 (Task type is set
to fixed work)
2) assign resource(s) to the task
3) save and publish the project
4) additional resource uses web access to assign the same task to
him/herself
5) project manager accepts the task in project
6) MSPS assigns the additional resource to the task, then splits the
time AND reduces the amount of work for the task. (the fixed work)
Our issue is with the reduction of the amount of work for a 'Fixed Work'
task. Why is the amount of work reduced? Any explanation of what is
happening?
Thanks
jmp