When you assign a resource in project server you have the option to choose
Request or Demand for that resource on a task in the Assign Resources dialog
box.

I need to know where in the sql tables I can pick up which option was
choosen on that assignment.

Thanks
Wesley
 
R

Rod Gill

Look in the pjdb.htm and pjsrvr.htm files: they are both in one of Project's
program folders. A vague memory suggests Request and Demand is only used
for Project Server.
 