G
George
I have the following situation which I have been able to handle in MSP
2003 but cannot figure out a way to do this in 2007:
The project has certain external customer tasks which I need to track
but for which we do not want to include work as this would distort our
budget, earned value etc.
The tasks have a duration, and should have progress tracked (%
complete) so we know how things are going. We need to show a customer
reource assigned to these tasks.
Soooo - the task has a duration, a resource assigned to it but no
effort/work.
Is this possible to set up?
I've tried every combination of fixed duration, fixed work, effort
driven, milestones marked, etc. etc but cannot seem to get a duration
to remain intact while reducing work to zero.)
Thanks in advance for any help!
2003 but cannot figure out a way to do this in 2007:
The project has certain external customer tasks which I need to track
but for which we do not want to include work as this would distort our
budget, earned value etc.
The tasks have a duration, and should have progress tracked (%
complete) so we know how things are going. We need to show a customer
reource assigned to these tasks.
Soooo - the task has a duration, a resource assigned to it but no
effort/work.
Is this possible to set up?
I've tried every combination of fixed duration, fixed work, effort
driven, milestones marked, etc. etc but cannot seem to get a duration
to remain intact while reducing work to zero.)
Thanks in advance for any help!