Assigned task Resource is different in Pro and resource's task lis

A

Angel Cisneros A.

Hello,
We are running Project Server 2003 and Project Pro 2003.
We have different Project Templates on project server according to project
size.
Whenever we publish a new project using a template, we assign a task
resource; the problem is that if we see the project on PWA after publishing,
the tasks show as unassigned! if we open the project on Project Pro the tasks
also appear as unassigned!
The strange thing is that the assigned resource receives the assigment
notification and the tasks appear on his task list.
This situation is annoying for PM, since they open the Project Plan and
see unassigned resource, then they assign a resource to the tasks and then
resource has duplicated tasks!
Any ideas why this is happening?

Thank you.
 