Assigned Task resource shows different in PWA and Project Pro 2003

A

Angel Cisneros A.

Hello,
We are running Project Server 2003 and Project Pro 2003.
We have different Project Templates on project server according to project
size.
Whenever we publish a new project using a template, we assign a task
resource; the problem is that if we see the project on PWA after publishing,
the tasks show as unassigned! if we open the project on Project Pro the tasks
also appear as unassigned!
The strange thing is that the assigned resource receives the assigment
notification and the tasks appear on his task list.
This situation is annoying for PM, since they open the Project Plan and see
unassigned resource, then they assign a resource to the tasks and then
resource has duplicated tasks!
Any ideas why this is happening?
 
M

Mike Glen

Hi Angel ,

Try posting on the server newsgroup as this one is closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top