Assigned Task Update Problems

M

mtbcpa

We use assigned tasks all the time, and it has been great. We upgraded to OL
2007 recently and made a custom form, and now we are having updating problems:

1. It seems that if one person assigns a task, and the second person assigns
it to someone else, udpates do not reach the original assignor, even though
they are on the update list. Does it matter if the subsquent assignor
checked the box to not receive updates?

2. We have created a custom form on a tab on our tasks, to track certain
items of data. That information does not seem to be updated when an assignee
makes changes. Is that just the way it works? Am I just out of luck?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top