Here's what I did:
In Project 2003:
1. Create a Test Project Plan
2. Created 4 tasks
3. Assigned Resource1 to Tasks 1,2 and 4
4. Assigned Resource2 to Task 3
5. Save and published the plan
6. Verified project is in PWA
7. Logged into PWA as Resource1
8. Home page did not indicate there were any tasks assigned to Resource1
9. My Tasks page does not indicate any tasks assigned to Resource1
10. Logged out, then logged in as Resource2 - no tasks assigned
What have I done wrong?