Assignement Data Different on Task Usage from Resource Usage View

B

BruceFFIC

Hi Project Server Users,

We are using PS 07 SP2 Aug09 MS CU.

I know I saw data on this issue, but have not been able to find it.

We are seeing different assignement data on the Task Usage view from
Resource Usage view for resources We are not using the Load Summary
Resource Assignments option.

I would appreciated pointing me to the data on this issue.

Thanks,
 
B

BruceFFIC

Hi Project Server Users,

We are using PS 07 SP2 Aug09 MS CU.

I know I saw data on this issue, but have not been able to find it.

 We are seeing different assignement data on the Task Usage view from
Resource Usage view for resources   We are not using the Load Summary
Resource Assignments option.

I would appreciated pointing me to the data on this issue.

Thanks,

I have a further clarification. Remember reading somewhere that Task
Usage View Baseline is based on the task's duration, while in the
Resource Usage View Baseline is based on the planned work. Can
someone confirm this assumption?

Thanks,
 
G

Gary L. Chefetz

Bruce:

Is it baseline data only that you are concerned about? There's lot's of
reasons why baseline data and baseline rollup data would be different
between the two. Think about what happens when you set a baseline on a task
that has a generic resource, and then switch the generic for an actual
resource.
 