When a PM publish a project plan that has team members assigned but the
assignment owner is set to a team leader, will the team members receives any
email notification of their assignments. The idea is we need to assign to
team members but only the team leader will report back the task progress.
This is so as the delegation of tasks in PS2007 differ than what it used to
be in PS2003. In 2003 the TL used to be able to delegate tasks and still be
able to track the progress reported from teh team members.
If there is any other way then I appreciate your help. Note that the status
manager is not a valid option as this will require the TL have full acces on
the project plan.
Thanks,
When a PM publish a project plan that has team members assigned but the
assignment owner is set to a team leader, will the team members receives any
email notification of their assignments. The idea is we need to assign to
team members but only the team leader will report back the task progress.
This is so as the delegation of tasks in PS2007 differ than what it used to
be in PS2003. In 2003 the TL used to be able to delegate tasks and still be
able to track the progress reported from teh team members.
If there is any other way then I appreciate your help. Note that the status
manager is not a valid option as this will require the TL have full acces on
the project plan.
Thanks,