D
dabevan
Hi,
I've got a task (TaskA) in my project that is going to take a fixed
number of man-days (ie work) to complete - say 50 man days (400 man
hours).
I've got Fred who has varying avaliability over the comming weeks. ie
he is 50% avaliable this week, 0% the next week, then 100% for a couple
of weeks, then back down to 50% for the remainder. ...I can set Freds
avaliability in the resource avaliability section.
I want to assign Fred to "Task A" and ask him to finish the task ASAP,
but if i assign him as 100% then MSProj only puts him on the tasks in
weeks when he is 100% avaliable.
....how do I get it to automatically assigning him as 50% in week 1, 0%
week 2, 100% weeks 3 & 4 and 50% for the remainder. (ie make as much use
of Fred as possible)?
Many Thanks
David Bevan
I've got a task (TaskA) in my project that is going to take a fixed
number of man-days (ie work) to complete - say 50 man days (400 man
hours).
I've got Fred who has varying avaliability over the comming weeks. ie
he is 50% avaliable this week, 0% the next week, then 100% for a couple
of weeks, then back down to 50% for the remainder. ...I can set Freds
avaliability in the resource avaliability section.
I want to assign Fred to "Task A" and ask him to finish the task ASAP,
but if i assign him as 100% then MSProj only puts him on the tasks in
weeks when he is 100% avaliable.
....how do I get it to automatically assigning him as 50% in week 1, 0%
week 2, 100% weeks 3 & 4 and 50% for the remainder. (ie make as much use
of Fred as possible)?
Many Thanks
David Bevan