I have some resources to whom I want to specify working time and non working
time like 3. august = 3 hours, 4. august = 2 hours etc. etc. I have created
the tasks with duration specified in hours and the resources with customised
calendars. However, no matter what i do MS Project only uses the 8 hour/ day
(weekend off) to calcuate the work and duration when applying the resources
to the task - what am I doing wrong - or is there something I misunderstand
about Project?
Thanks,
Ole