I am looking at delaying the start of an assignment and have so far used the
Delay field in the Resource or Task form. I see there is also a Levelling
Delay field – this doesn’t seem to get changed automatically if I enter a
levelling delay for a task in the Resource Allocation View nor if I get
Project to level tasks using Tools, Resource Levelling, so I guess they must
be for something else. They also seem to want only normal day entries not
elapsed days.
What is the point of this Levelling Delay field for assignments and when
should I be using it?
Hoping someone can shed some light on this.
Delay field in the Resource or Task form. I see there is also a Levelling
Delay field – this doesn’t seem to get changed automatically if I enter a
levelling delay for a task in the Resource Allocation View nor if I get
Project to level tasks using Tools, Resource Levelling, so I guess they must
be for something else. They also seem to want only normal day entries not
elapsed days.
What is the point of this Levelling Delay field for assignments and when
should I be using it?
Hoping someone can shed some light on this.