Assignment Details in PWA 2007

R

Robert

Hello,

For some tasks, the Assignment Details page shows a grid for the 5 days of
the week in the Task Progress section
For some other tasks, the Assignment Details page shows only the Total Work
and the Percent complete.
Why ?
NB : The tracking method is the same for all the projects : Work hours / Day
(Timesheet)
Thanks ahead.

Robert
 
M

Marc Soester [MVP]

Hi Robert,

The only explanation is that the PM has changes the tracking method. You can
avoid this by forcing the tracking method to the one you specify.
Hope this helps
 
R

Robert

Thanks Marc,
I'll check that!
Robert

Marc Soester said:
Hi Robert,

The only explanation is that the PM has changes the tracking method. You
can
avoid this by forcing the tracking method to the one you specify.
Hope this helps
 
G

Gérard Ducouret

Hi,
Proposals don't obey the Tracking method set by the administrator in Server
Settings / Task Settings and display. For Proposals, the tracking method is
fixed : Percent of work done per period.

Gérard Ducouret
 