Assignment Details Page Default Work in Days

D

Darrell

Using Project Server 2007...

In PWA, on the Assignment Details page, in the General Details section under
Task
Progress, the "Total Work" and "Timephased Work" are expresses as days. Can
this be changed to hours?

Thx,
Darrell
 
P

Paul Conroy

browse to my tasks page and open the properties of the web part from the site
actions button (top right of page), edit, modify shared web part

under the Project Web Access section you have the option to set the duration
and work format
 
D

Darrell

Paul,

I have set the format for work and duration to hours and on the My Tasks
page all assignments show in hours. However, when you open a task assignment
in the Assignment Details view the fields for "Total Work" and "Timephased
Work" are still in days. It is these fields I wish to chaneg as well. Any
idea where this can be done?

Darrell
 