For any task, in the Assignment Details page (Hours of work done per
period), I can't edit any Actual work cell. The Save button and the
Recalculate button are greyed out.
What could be the problem?
Thanks ahead
 
D

Dale Howard [MVP]

Robert --

I believe this indicates that your Project Server administrator has selected
the Time Entry By Timesheet Only option for your Project Server system.
Check with him/her to confirm whether this is true and let us know what you
find.
 
R

Robert

Great!
That was really this option : Time entry by Timesheet only (in Task Settings
and Display )
Thanks a lot Dale !
 