Z
zerogate
Hi again
Is it possible to let my MS Project App calculate ressource units
automatically or at least configure them to be dynamic?
My problem is, that I have one ressource working on two tasks which
overlap.
So I want to assign 100% of the ressource while there is only one task
running and when the second one starts i need 50% of the ressource for
that one thus either of the two tasks should only 50% of the
ressource.
Is this possible?
Is it possible to let my MS Project App calculate ressource units
automatically or at least configure them to be dynamic?
My problem is, that I have one ressource working on two tasks which
overlap.
So I want to assign 100% of the ressource while there is only one task
running and when the second one starts i need 50% of the ressource for
that one thus either of the two tasks should only 50% of the
ressource.
Is this possible?