Hello,

When I insert the Assignment Owner field in the Task Usage view or in any
other view in Project Pro 2007, the drop-down list is grayed out: I'm not
able to change the Assignment Owner. Why?
Thanks for any idea
 
M

Marc Soester [MVP]

Robert, taht is most likely the case because you dont have resources assigned
to your schedule that can become assignement owners. Do you have any global
resources assigned to your schedule?
 
R

Robert

Thanks a lot Marc,

You are right: I was not well awaked: in this project, most of the resources
are local resources! (Not Enterprise resources)