MS Project is forcing one of my week days to be only 7 hours long. I have 4 tasks at 2 hours each for three days. The first day it displays the work and duration for each assignment as 2h, 2h, 2h, and then 1h - can't figure out why? It should be 2h, 2h, 2h, and 2h - for an 8 hour day. It's throwing off the rest of the schedule by one hour, so the last day the resouce is working only one hour! There is only a single resource and he is at 100% and is not over allocated.