Y
Yaara Intel Planning
i am using "fix units" for all my tasks, the assignment basic units are 100%
and accordingly the schdule is 1d per day. the problem is, when a user update
progress through PWA more than 1d per assignment, the assignment units
changes accordingly and so does the schedue.
e.g. my task is 5 days --> project schedules it to start on monday and end
on friday(1 day per day). after the resource updated progress on the task -2
days. the assignment looks like that: resource[200%] and it schedule 2 days
per day.
the weird thing is, it doesnt happen to all the tasks. can you help me
understand why this is happening and how can i fix it? (other than delete the
units manually)
thanks
Yaara
and accordingly the schdule is 1d per day. the problem is, when a user update
progress through PWA more than 1d per assignment, the assignment units
changes accordingly and so does the schedue.
e.g. my task is 5 days --> project schedules it to start on monday and end
on friday(1 day per day). after the resource updated progress on the task -2
days. the assignment looks like that: resource[200%] and it schedule 2 days
per day.
the weird thing is, it doesnt happen to all the tasks. can you help me
understand why this is happening and how can i fix it? (other than delete the
units manually)
thanks
Yaara