G
G Lykos
Greetings! Discovered that a schedule I'm maintaining somehow has some
resource assignment start and finish dates that are drastically different
than task start and finish dates. Am going through doing a manual
comparison and setting the assignment dates equal to task dates.
Question 1: Any idea how this situation might have occurred? (No special
resource calendars in use)
Question 2: I would like to be able to filter, or create a VBA comparison
loop, to identify all assignments and/or tasks where the assignment start
and finish dates are different than the task dates. However, I don't see a
way to set up either. Any ideas?
Thanks,
George
resource assignment start and finish dates that are drastically different
than task start and finish dates. Am going through doing a manual
comparison and setting the assignment dates equal to task dates.
Question 1: Any idea how this situation might have occurred? (No special
resource calendars in use)
Question 2: I would like to be able to filter, or create a VBA comparison
loop, to identify all assignments and/or tasks where the assignment start
and finish dates are different than the task dates. However, I don't see a
way to set up either. Any ideas?
Thanks,
George