G
Gil
Hi,
Sometime entering actual work for an assignment, changes the
assignment units in the gantt chart to look like DEVELOPER[300%] or
DEVELOPER[25%] even though the original assignment was the default
100%.
I have found some post about this issue, but with no explanation for
the reasoning or a solution.
I am bothered by this behavior because before I can level resources I
need to go through the entire plan, search for this issue and change
it back to the original assignment units.
Any suggestions?
Thanks,
Gil
Sometime entering actual work for an assignment, changes the
assignment units in the gantt chart to look like DEVELOPER[300%] or
DEVELOPER[25%] even though the original assignment was the default
100%.
I have found some post about this issue, but with no explanation for
the reasoning or a solution.
I am bothered by this behavior because before I can level resources I
need to go through the entire plan, search for this issue and change
it back to the original assignment units.
Any suggestions?
Thanks,
Gil