M
Mike F
Background: We are working in a Project 2007 environment. We use Fixed
Units, only 1:1 task-to-resource assignment relationships, and let the task
effort determine our schedule duration and dates. We assign only work in
hours and report progress via actual hours through the task usage sheet. We
assign each resource an Assigned Unit of generally 60%, 75%, or 100% on a per
project/task basis. We re-schedule unfinished work forward each week and
level resources with their appropriate assigned units. We do this in a master
project with selected projects inserted.
Question: After taking progress each week, resources assigned units change
and are displayed along with the resource name for those less than 100%.
Prior to scheduling and leveling for the new week, do we need to re-set each
resource's assigned units back to their desired value for each task for
"remaining work" to be scheduled and leveled forward correctly. Or, is there
a way around having to re-set these each week (prior to schedule and level)?
Units, only 1:1 task-to-resource assignment relationships, and let the task
effort determine our schedule duration and dates. We assign only work in
hours and report progress via actual hours through the task usage sheet. We
assign each resource an Assigned Unit of generally 60%, 75%, or 100% on a per
project/task basis. We re-schedule unfinished work forward each week and
level resources with their appropriate assigned units. We do this in a master
project with selected projects inserted.
Question: After taking progress each week, resources assigned units change
and are displayed along with the resource name for those less than 100%.
Prior to scheduling and leveling for the new week, do we need to re-set each
resource's assigned units back to their desired value for each task for
"remaining work" to be scheduled and leveled forward correctly. Or, is there
a way around having to re-set these each week (prior to schedule and level)?