B
bgriffwork
I have a question about the Assignment Units column in the Resource Usage
view in Project Pro 2003. It seems that this field behaves as a resource
(future) allocation percentage until Actual Work is posted against a task,
then it behaves as a high-water mark resource (current) utilization
percentage. It seems that this field will go up but not down, and cannot
always be modified once Actual Work is entered.
I have the need to be able to either: 1) reset this column to reflected
adjusted allocation percentages, or 2) use this figure to predict future
resource allocations for each task.
Any suggestions would be appreciated.
view in Project Pro 2003. It seems that this field behaves as a resource
(future) allocation percentage until Actual Work is posted against a task,
then it behaves as a high-water mark resource (current) utilization
percentage. It seems that this field will go up but not down, and cannot
always be modified once Actual Work is entered.
I have the need to be able to either: 1) reset this column to reflected
adjusted allocation percentages, or 2) use this figure to predict future
resource allocations for each task.
Any suggestions would be appreciated.