D
David
I have a Generic Resource which has Max Units set to 60%. the PM has set the
Assignments Units 150%. (Don't ask, or is this the issue?)
1. We do not use Admin Projects or Overtime.
2. Why doesn’t leveling apply more than Max Units to the task or does
leveling do anything at all to units?
3. How can I get Leveling to apply the extra hours in a single workday?
4. I am trying to get just a few tasks within a project with several hundred
task, to apply a constant duration to the execution of the tasks. Any
suggestions?
5. Our goal is to set up a testing effort which works 24 hours a day for 96
straight hours.
6. I have the task(s) set up for 96 work hours with a 24 hour by 5 day a
week calendar set up. Leveling appears to adjust the task duration, in this
scenerio. It changes the duration from the initial setup of 4 calendar work
days to something else, a longer calendar time.
7. How can I set up the task(s) to provide this constant duration regardless
of the leveling specified calendar start date?
Thanks in advance for any input!
Assignments Units 150%. (Don't ask, or is this the issue?)
1. We do not use Admin Projects or Overtime.
2. Why doesn’t leveling apply more than Max Units to the task or does
leveling do anything at all to units?
3. How can I get Leveling to apply the extra hours in a single workday?
4. I am trying to get just a few tasks within a project with several hundred
task, to apply a constant duration to the execution of the tasks. Any
suggestions?
5. Our goal is to set up a testing effort which works 24 hours a day for 96
straight hours.
6. I have the task(s) set up for 96 work hours with a 24 hour by 5 day a
week calendar set up. Leveling appears to adjust the task duration, in this
scenerio. It changes the duration from the initial setup of 4 calendar work
days to something else, a longer calendar time.
7. How can I set up the task(s) to provide this constant duration regardless
of the leveling specified calendar start date?
Thanks in advance for any input!