Assignment View Issue

M

MARVS

I modified the assignment view in PWA and added the baseline duration,
baseline work and the task status (enterprise custom field) field. However,
when I checked it in resource>>view resource assignment, the values from the
fields that I added are not showing up.

Please help.
 
D

Dale Howard [MVP]

MARVS --

Assignment views are based on the same information shown on the View My
Tasks page. To see this information, you need to do the following with
every project in your Project Server database:

1. Open the project.
2. Click Tools - Customize - Published Fields.
3. Add the three fields to the list on the right.
4. Click the Set as Default button.
5. Click the OK button.
6. Click Collaborate - Publish - Republish Assignments and then click the
OK button.

You might want to try this with only one project to confirm that it actually
works for you. Hope this helps.
 