Assignments displayed in "All assignments" mode

R

Rabbit

All,

PM usually save the link in "View resource assignments" of Resource, and
then PM click the saved link to view the timesheet of team in Resources
function of PWA, but the default page is always displayed in "Current
assignments" mode, sometimes it makes PM confusion, how can we set the
default display page in "All assignments" mode when PM save the link?

Thanks in advance,
Rabbit.
 
D

Dale Howard [MVP]

Rabbit --

To the best of my knowlege, when you save a link in the View resource
assignments page the system never saves the "All assignments" option in the
link. I believe your best option would be to train your PM's to select the
"All assignments" option when they display a link. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the books on Project Server"
 